Medical facility construction in the U.S. runs from roughly $250 per square foot for a lean dialysis center to well over $1,000 for a new hospital tower. For a hospital, Gordian's RSMeans data puts the national average at $439.85 to $454.33 per square foot for a two- to three-story building. Outpatient space, renovations and dialysis centers land in different places, and the final number depends on scope, building condition, location and what the estimate leaves out. A general contractor who prices occupied-building and healthcare work every year can turn those ranges into a budget for your site. That is what we do at Expert Building Maintenance (EBM), based in Burr Ridge since 2001.
Key Takeaways
- Published figures are planning models. Hospital averages are about $440 to $455 per square foot, new healthcare construction benchmarks near $700 to $730, and outpatient fit-outs average $412.
- Renovation is cheaper than new construction. A gut-and-rebuild runs roughly 55% of new construction cost, and a moderate renovation roughly 35%.
- Construction is only about 60 to 65% of a project's total cost, so owner costs, design and contingency must be added.
- Location matters. Gordian's 2025 hospital data put Chicago at $540.50 per square foot against a national average of $451.11.
- Early involvement of a contractor produces a more reliable number than a database figure alone.
Table of Contents
- What medical facility construction costs per square foot
- Ground-up, renovation or interior build-out
- What a dialysis center costs
- Why location moves the number
- What pushes the cost up
- What the per-square-foot number leaves out
- How to build a budget you can defend
- Timeline and cost are linked
- Planning a medical project with EBM
- FAQ
What medical facility construction costs per square foot
The first thing to understand is that "medical facility" covers very different buildings, and the per-square-foot figure you find online usually belongs to just one of them.
| Facility type | Reported range | Source basis |
|---|---|---|
| Hospital, 2 to 3 stories | $439.85 to $454.33 per SF | RSMeans 2026 |
| New healthcare construction, general benchmark | $700 to $730 per SF | Construction consultancy benchmark, 2024 |
| Medical outpatient fit-out, national average | $412 per SF | JLL, 2026 |
| Healthcare interior build-out | Mid-$100s to $400+ per SF | Industry guides, 2026 |
Why do the hospital and the "new healthcare" figures differ by about $250 per square foot? They come from different methods. The RSMeans number is a planning model built from structural system and exterior materials. The $700 to $730 benchmark includes site development and parking, and it is stated before contingencies and escalation. Neither is a bid.
The Gordian figures are explicitly for planning and budgeting, not detailed estimates. Building Design+Construction's 2026 summary also reports that the national average for new commercial hospital construction is more than 25% above 2021 levels, with sharp increases in the first half of 2026. Use a published range to decide whether a project is feasible. Do not use it to set a final budget.
Ground-up, renovation or interior build-out
The single biggest lever on your budget is the type of work.
New construction. You pay for site work, foundations, structure, envelope and every system. That is why the consultancy benchmark above sits near $700 to $730 per square foot for new healthcare buildings.
Renovation. The same benchmark puts a gut-and-rebuild renovation at roughly 55% of new construction cost and a moderate renovation at roughly 35%. Applied to $700 to $730, that is about $385 to $400 per square foot for a gut renovation and $245 to $255 for a moderate one. Demolition of older buildings adds roughly $20 to $50 per square foot.

The renovation tiers are worth knowing. Healthcare Facilities Today describes heavy renovation as removing everything except the primary structure and envelope, moderate renovation as upgrading about half the building, and light or cosmetic work as minor. Know which tier you are in before comparing any two numbers.
Tenant build-out. A medical tenant improvement is a fit-out inside an existing shell. JLL's 2026 benchmarking puts the national average all-in fit-out for medical outpatient space at $412 per square foot. New medical office building starts are at a record low of 1% of inventory, and most of those are pre-leased, so more of the market is moving to renovation and adaptive reuse. In that kind of project, phasing, off-hours work and labor conditions are significant parts of the price.
Economic uncertainty pushes in the same direction. Gordian notes that many healthcare organizations are favoring renovations and incremental upgrades to manage risk and get more from the facilities they already have.
For a closer look at this kind of work, see our medical office renovation scope, cost and planning guide and our urgent care buildout guide.
What a dialysis center costs
Dialysis operators ask this often, and two public projects show how wide the range is.
- A 10,488-square-foot center with 16 hemodialysis chairs at Citizens Memorial Hospital had a construction cost of $7.3 million, with construction starting in November 2024 and a ribbon-cutting in December 2025. That works out to about $700 per square foot.
- A Fresenius Kidney Care center in Denton, Texas, of about 11,100 square feet was reported at about $3.2 million, or roughly $288 per square foot, based on state licensing documents reported in June 2026.
Two buildings of nearly identical size, a gap of more than $400 per square foot. The difference is rarely one thing. Hospital-affiliated projects, ground-up versus leased-space work, the amount of water treatment and plumbing infrastructure, finishes and local labor all play a part. A budget for your center needs your own program: chair count, water treatment room, patient flow, and whether you are building in a shell or converting existing space.
Our dialysis center construction and buildout services cover that scope, and our DaVita dialysis buildout project page shows work in Wisconsin and Michigan.
Why location moves the number
RSMeans states that construction costs can vary 20% to 50% or more between states and cities. Gordian's 2025 hospital data shows it clearly:
| Market | Hospital cost per SF (2025) |
|---|---|
| New York | $582.21 |
| Chicago | $540.50 |
| Los Angeles | $520.83 |
| Boston | $513.62 |
| Omaha | $407.60 |
| Denver | $401.93 |
| Houston | $373.81 |
| National average | $451.11 |
These come from Gordian's 2025 healthcare report. Chicago sits about 20% above the national average. If you are using a national benchmark for a Chicago-area project, adjust it upward before you take it to a lender or board. For local context on commercial work generally, see our guide to commercial renovation costs in Illinois.
JLL also points to regional pressures such as seismic retrofitting in California and heavy construction volume in Texas.
What pushes the cost up
Clinical intensity. JLL reports that fit-outs for high-acuity services rise sharply because of advanced mechanical, electrical and plumbing (MEP) systems, equipment integration and structural accommodation. A primary care suite and a procedure or imaging suite are not the same cost class.
Mechanical, electrical and plumbing systems. RSMeans says hospital costs are driven largely by MEP systems, skilled labor and regulatory requirements. Medical gas, dedicated HVAC, power backup and plumbing density all raise the budget.
Existing building condition. In a renovation, the age of the building and the quality of its drawings decide how much you hold in contingency. Unknown conditions behind walls and above ceilings are where renovations lose money.
Occupied-building phasing. If your facility stays open during construction, you may need temporary partitions, protected egress, after-hours utility work and infection control procedures. These should appear as line items in your budget, not be absorbed into the scope. EBM specializes in renovating occupied buildings and coordinates construction activity to minimize disruption to daily operations, which is why phasing is part of how we plan skilled nursing and healthcare work from the start. See our skilled nursing facility renovations.
Equipment and finishes. Published ranges for medical office work put exam room finish-out in the $8,000 to $15,000 range and imaging rooms from $200,000 to $1 million, according to an industry cost summary. Treat these as order-of-magnitude figures that depend on your equipment.
Schedule. Longer schedules carry longer exposure to escalation. A published cost model is also historical by nature, and the Building Construction People article argues such databases can lag current pricing by six to eighteen months. That is a strong reason to bring a contractor into pricing early.

What the per-square-foot number leaves out
This is where budgets fail. The construction figure is not the project total.
The consultancy benchmark above states that construction cost is only about 60 to 65% of the total project cost. Owner costs and contingency must be added on top. Healthcare Facilities Today describes a typical soft cost multiplier of 1.35 to 1.45 times construction cost (from a 2018 article, so treat it as a structure, not a current price), and furniture, fixtures and equipment (FF&E) ranging from about 10% of construction cost for an administrative department to 35% for a new birthing center.
In practice, check each of these before you accept any estimate:
- Land and site work
- Architectural and engineering fees
- Permits and fees
- Demolition and abatement
- Movable medical equipment and FF&E
- Financing
- Contingency
- Escalation to the start date
A worked example
Say you are fitting out 10,000 square feet of outpatient space. At JLL's national average of $412 per square foot, construction alone is $4,120,000. If that is 60 to 65% of the project total, the full project is closer to $6.3 million to $6.9 million. Add Chicago's location premium and any clinical intensity, and the figure moves again. The point of this exercise is not precision. It is that a number that looks right at $412 can be a third lower than the real commitment.
How to build a budget you can defend
- Define the program. Write down the rooms, equipment, chair or exam counts and clinical services. Cost follows program.
- Pick the work type. Decide between ground-up, gut renovation, moderate renovation or tenant build-out, and use the matching benchmark.
- Adjust for location. Apply a local factor. Chicago, for example, sits well above the national hospital average.
- Add the excluded costs. Use the checklist above, and build soft costs on top of construction.
- Size contingency to the building. Older buildings and poor drawings need more.
- Price phasing. If you operate during construction, price the temporary protection and after-hours work.
- Get contractor input before design is final. The Building Construction People article advises taking the primary budget number from a contractor under a preconstruction arrangement, using independent estimates as a cross-check at design development. A general contractor can price alternatives while changes are still cheap.
Our commercial construction management and coordination service covers project management and trade coordination from planning and demolition through final turnover, and our project timeline page shows how that sequence runs.
Timeline and cost are linked
A budget that ignores schedule is incomplete. Longer approvals and phased work extend general conditions and exposure to price changes. Our commercial building renovation guide walks through scope, cost and process for occupied buildings, and our office renovation cost guide is useful if your project mixes clinical and administrative space.
Planning a medical project with EBM
EBM is a full-service commercial general contractor serving Chicagoland, Illinois and the Midwest. Our healthcare work includes skilled nursing facility renovations, dialysis center buildouts, medical office buildouts and healthcare facility renovations, and we manage projects from initial planning and demolition through construction and final turnover. We emphasize clear communication, hands-on project management and reliable trade coordination, and we tailor solutions to each client's goals, budget and schedule.
If you have a program and a site, we can talk through scope and phasing and give you a number built for your building, not a national average. Start with our services overview or see our completed projects.

FAQ
How much does it cost to build a medical building?
It depends on the type. Outpatient medical fit-outs average about $412 per square foot nationally according to JLL, new healthcare construction is often benchmarked near $700 to $730 per square foot, and hospitals average roughly $440 to $455 in RSMeans planning models. Add owner costs and contingency to any of these.
How much does it cost to build a dialysis center?
Public projects show a wide spread. A roughly 11,100-square-foot Texas center was reported at about $3.2 million, while a 10,488-square-foot hospital-affiliated center cost $7.3 million. Your number depends on chair count, water treatment and plumbing, and whether you are converting existing space or building new.
Is renovating a medical facility cheaper than building new?
Generally, yes. A construction consultancy benchmark puts gut-and-rebuild renovation at about 55% of new construction cost and moderate renovation at about 35%. Phasing, infection control and the condition of the existing building should be priced into the renovation budget.
Why is Chicago more expensive than the national average?
Local labor rates and market conditions matter. Gordian's 2025 hospital data put Chicago at $540.50 per square foot against a national average of $451.11. Use a local adjustment whenever you start from a national benchmark.
How long does medical facility construction take?
It varies with scope. Tenant build-outs are shorter than ground-up work, and imaging or procedure space takes longer than basic exam space. Approvals and phasing in occupied buildings also affect the schedule, so ask your contractor for a sequence early in planning.