Most commercial construction work in the United States is contracted in one of five ways: fixed price (lump sum), cost-plus, guaranteed maximum price (GMP), time and materials, or unit price. The right choice depends on how well your scope is defined and who you want to carry the cost risk. A defined scope usually points to a fixed price. An uncertain scope points to cost-plus with a cap, or to time and materials. At Expert Building Maintenance, we have been a Chicago-area commercial general contractor since 2001, and the contract conversation is where a good project starts.
Key Takeaways
- A contract type decides who pays when costs move. A delivery method (design-build, CM at risk, integrated project delivery) decides how the project is organized. You choose both.
- Lump sum fits a fully drawn scope: the contractor carries the overrun risk, and you pay the same amount unless a formal change order alters the scope.
- Cost-plus and GMP fit projects where the scope is still forming. GMP adds a ceiling, but only as firm as its stated exceptions.
- Time and materials suits small or hard-to-scope work, and unit price suits repetitive work with uncertain quantities. A cap or not-to-exceed figure keeps both predictable.
- Whatever the type, the clauses on change orders, allowances, retainage, schedule of values and schedule decide how the contract behaves in practice.
Table of Contents
- Contract Type vs. Delivery Method: Two Different Decisions
- Lump Sum (Stipulated Sum) Contracts
- Cost-Plus Contracts
- Guaranteed Maximum Price (GMP) Contracts
- Time and Materials Contracts
- Unit Price Contracts
- Design-Build, CM at Risk and Integrated Project Delivery
- The Five Payment Structures Side by Side
- How to Choose for Your Kind of Project
- Clauses That Matter More Than the Label
- Why the Contractor Matters as Much as the Contract
- Work With a General Contractor on Your Next Project
- FAQ
Contract Type vs. Delivery Method: Two Different Decisions
Owners often mix up two questions. The Construction Management Association of America (CMAA) separates a contracting format from a project delivery method: the contracting format allocates cost or performance risk between the parties, while the delivery method organizes how the project gets completed and may use one or more contracting formats.
In plain terms:
- Contract type (payment structure): fixed price, cost-plus, GMP, time and materials, unit price. This answers "how do I pay, and who absorbs surprises?"
- Delivery method (project organization): design-bid-build, design-build, CM at risk, integrated project delivery. This answers "who is under contract with whom, and when does the builder get involved?"
A CM-at-risk project, for example, often pays through a GMP. A design-build project can be priced lump sum or GMP. Pick the payment structure first for a clear project, or the delivery method first for a complex one, but settle both before signing.
Lump Sum (Stipulated Sum) Contracts
In a lump-sum contract, the contractor agrees to complete defined work for a fixed price. CMAA notes that this price is commonly paid periodically, by stages of completion or milestones stated in the contract.
Who carries the risk. The AIA explains that the contractor generally absorbs labor and material overruns through reduced profit, and keeps the extra profit if actual costs come in below the estimate. You pay the same amount unless the scope changes through a formal change order.
Where it fits. Office buildouts, tenant improvements and renovations with complete drawings and specifications. Budget certainty is the main benefit, and it is real only when the documents are complete.
Where it goes wrong. Incomplete drawings. When the scope is vague, every gap becomes a change order, and the "fixed" price drifts. Before you sign, make sure the scope, exclusions, allowances and alternates are written down line by line.
A worked example. Say a 10,000-square-foot office buildout has complete drawings and a lump-sum price of $1,000,000. If lumber, labor or drywall run 5% over the estimate, the contractor absorbs it. If you then ask for an added conference room, a change order adds the cost and time. The numbers here are illustrative, not a market price.
Cost-Plus Contracts
Under cost-plus, you pay the contractor's actual, documented cost of the work plus a fee. CMAA describes the fee as either a percentage of cost or a flat fee paid proportionally with periodic payments. The Construction Industry Institute identifies six reimbursable strategies: cost-plus percentage fee, incentive fee, award fee, fixed fee, cost-plus GMP and convertible reimbursable contracting.
Who carries the risk. You do. The owner has more cost variability, which is the trade-off for starting before the design is final and for seeing every cost.
Where it fits. The same institute says reimbursable contracting can suit work where fixed pricing does not, because of substantial uncertainty, new technology, variable labor markets or volatile material prices. Think of a renovation in an older building where conditions behind the walls are unknown until demolition.

What the contract must define. CMAA says the agreement should spell out allowable costs, the fee, audit or open-book rights, contingency, savings sharing and GMP exceptions. A percentage fee and a fixed fee behave differently. With a percentage fee, the fee grows as costs grow. A fixed fee does not, so many owners prefer it when the scope is still moving.
Guaranteed Maximum Price (GMP) Contracts
A GMP contract keeps the cost-plus structure but adds a ceiling. The owner pays documented actual costs and the contractor's fee up to that maximum. Georgia's public construction-management agreement, for example, states that payment may not exceed the GMP, subject to the contract's defined contingencies and adjustments. CMAA adds that the contractor bears costs above an enforceable GMP unless the contract permits an adjustment.
Two details decide whether a GMP protects you:
- The exceptions. A GMP is only as firm as its stated contingencies, exclusions and change provisions. Read them as carefully as the number.
- Savings sharing. AIA's 2024 design-build instructions show that the GMP contract sum comprises the cost of the work plus the design-builder's fee, and that specific provisions may address how the builder shares in savings below the GMP. Know in advance who keeps what is left over.
A GMP is typically set when design is far enough along to price. AIA's owner guidance says owners should weigh the completeness of design information, the contingency and their own willingness to share cost-overrun risk when considering CM at risk with a GMP.
Time and Materials Contracts
Time and materials (T&M) pays for labor, equipment, materials and services plus a fee. AIA says it works for small projects or where the exact scope is hard to anticipate, and that a not-to-exceed amount or cap can provide certainty.
In practice, labor is billed at an established hourly or daily rate, and materials are reimbursed. Material charges may include freight and markup, while labor rates may include overhead, administration and profit. Ask exactly what each rate includes.
Where it fits. Small repairs, punch-list work, investigative work and tasks that appear mid-project. Where it goes wrong. Without a cap, the total is open-ended. Require a not-to-exceed figure, approved rates and timesheet documentation.
Unit Price Contracts
Unit-price contracting suits work whose type is defined but whose quantity is not. CMAA says the contractor bids a price for each specified unit, such as a cubic yard of paving material. AIA describes it as a fixed price for each repeated unit, suited to civil, utility and infrastructure work like pipe or roadway construction when quantities cannot be accurately determined in advance.
Unit prices include labor, materials, overhead and a markup for profit, and you pay for additional units if more are needed. For most interior commercial projects this is a supplement rather than the main structure: it can price a line item such as extra drywall repair or added floor prep whose quantity is unknown until demolition.
Design-Build, CM at Risk and Integrated Project Delivery
These appear on every list of contract types, but they are delivery methods, not payment structures. Each still needs a price mechanism such as lump sum or GMP.
- Design-build. CMAA says the owner contracts under one agreement for consolidated design and construction services rather than hiring designer and builder separately. One party answers for both.
- CM at risk. AIA says the construction manager provides preconstruction advice and then takes on the financial obligation for construction under a specified cost agreement, often a GMP, while the architect stays under a separate contract. The same primer cautions that "at risk" can mean holding the trade contracts and performance risk, or it can mean a cost guarantee. The contract must say which.
- Integrated project delivery (IPD). The AGC/AIA primer defines it as a contractual arrangement among at least the owner, constructor and design professional that shares financial risk and reward based on project outcomes. It is built on early involvement, fiscal transparency and shared decision-making, and it is most often chosen for large, complex projects.
The Five Payment Structures Side by Side
| Contract type | Who carries cost overruns | Best when | Watch for |
|---|---|---|---|
| Lump sum | Contractor | Scope and drawings are complete | Gaps in documents turning into change orders |
| Cost-plus (percentage or fixed fee) | Owner | Scope is uncertain or evolving | Undefined allowable costs, no audit rights |
| Cost-plus with GMP | Owner up to the GMP, contractor above it | Design is advanced but not final | Exceptions and contingency that weaken the cap |
| Time and materials | Owner, unless capped | Small or hard-to-scope work | No not-to-exceed amount, vague rate definitions |
| Unit price | Owner for quantity, contractor for unit price | Repetitive work, uncertain quantities | Quantity estimates far from reality |
How to Choose for Your Kind of Project
Office buildouts and tenant improvements. Drawings are usually complete before bidding, so lump sum is the natural fit. Your tenant lease often has a work letter and a move-in date, which makes price and schedule certainty the priority.
Occupied healthcare, senior living and skilled nursing renovations. Work happens around residents, patients and staff, and existing conditions are rarely fully known. A GMP or cost-plus structure with a defined contingency can fit here, because the budget needs a ceiling while the scope may shift when walls open. Phasing, infection control and life-safety requirements should be written into the scope so they are priced, not discovered.
Dialysis and medical office buildouts. Specialized plumbing, electrical and equipment coordination makes early contractor input valuable. Design-build or CM at risk with a lump sum or GMP price lets cost be tested while the design is still flexible.
Condominium common areas and multifamily. A board needs a fixed number to present to owners, so lump sum with clearly priced allowances and alternates is the usual route.
Ground-up construction and additions. Large and long-running, these often use GMP, sometimes with design-build or CM at risk. The earlier the builder joins the design team, the better the GMP can be set.
A quick test: if you can hand three contractors the same complete set of drawings and expect comparable bids, ask for lump sum. If you cannot, you are buying judgment and transparency, so look at GMP or cost-plus.

Clauses That Matter More Than the Label
Two owners can both sign a "GMP contract" and have very different outcomes. These provisions do the work.
Change orders
The American Bar Association's construction-clause guidance says change-order provisions should state the procedure for adjusting payment and contract time, and that an agreed change order should settle matters relating to the changed work. Insist that every change has a written price and a schedule effect before work starts.
Allowances
Allowances are placeholders for items not yet selected, such as finishes or fixtures. A University of Houston System CM-at-risk agreement illustrates the standard approach: allowances are preliminary estimates, and the construction manager must provide a detailed cost breakdown and obtain owner authorization before spending them. Decide selections early so allowances do not become overruns.
Schedule of values and retainage
AIA describes a schedule of values as a line-item breakdown of the contract sum used to measure completed work and support payment applications, particularly for stipulated-sum and GMP contracts. Retainage is withheld from progress payments as financial security against incomplete or defective work. The same source says the contract should state the amount withheld and the release conditions, subject to state law. Illinois owners should have counsel confirm how state law applies.
GMP basis and schedule
A comparison chart of standard design-build forms lists the items a GMP basis should capture: cost of the work, fee, trade categories, allowances, contingencies, alternates, unit prices and assumptions. One of the standard forms adds completion dates, the schedule and a deadline for accepting the GMP. If the price is only valid for a limited window, you should know it before the design is finished.
Why the Contractor Matters as Much as the Contract
A contract type only allocates risk on paper. How a contractor runs the job decides whether risk becomes a dispute. In commercial buildouts and renovations, the daily work is trade coordination, sequencing, and keeping an occupied building working. EBM manages projects from initial planning and demolition through construction and final turnover, and coordinates construction in occupied buildings to minimize disruption to daily operations. Our commercial construction management and coordination approach puts hands-on oversight behind whichever contract structure fits your project. For the trade side, see how we handle subcontractor coordination, and why one general contractor often beats hiring trades separately.
If you are comparing firms, our guide to choosing a commercial general contractor in Illinois lists the questions to ask, and our project timeline shows how the phases fit together.
Work With a General Contractor on Your Next Project
EBM is a full-service commercial general contractor in Burr Ridge, Illinois, serving the Greater Chicago area, Illinois and the Midwest. We handle office buildouts, tenant improvements, healthcare and skilled nursing renovations, dialysis center buildouts, condominium common area improvements, code compliance work and select ground-up construction, with solutions tailored to your goals, budget and schedule. See the full list on our commercial construction services page.

If your project is an office or tenant space, start with commercial office buildouts and tenant improvements. For healthcare work, see dialysis center buildouts or skilled nursing facility renovations. Bring your drawings, or your plans so far, and we will talk through your scope and schedule.
FAQ
What is the most common type of construction contract?
The fixed-price contract, also called lump sum or stipulated sum, is the most widely used. The contractor agrees to a set price for defined work, and you pay that amount unless a formal change order alters the scope. It works best when drawings and specifications are complete.
What is the difference between a GMP and a lump-sum contract?
In a lump-sum contract, the price is fixed and the contractor absorbs normal cost overruns. In a GMP contract, you pay documented actual costs plus a fee, up to a maximum. GMP is more flexible while design is developing, and the exceptions and contingencies determine how firm the maximum is.
Is design-build a type of construction contract?
It is usually classed as a project delivery method. Design-build puts design and construction under one agreement, and that agreement still needs a pricing structure such as lump sum or GMP. So you choose a delivery method and a payment type together.
When should I use time and materials?
Use it for small projects or work whose scope is hard to predict in advance. Ask for a not-to-exceed amount, agreed hourly or daily rates and documented timesheets, so the total stays predictable.
Do I need a lawyer to review a construction contract?
For commercial projects, yes. Have your attorney review the final agreement, especially indemnity, payment, retainage and dispute clauses, since they depend on Illinois law and your specific project. Your general contractor can walk through scope, schedule and pricing with you.